There’s Road Work In Progress On SR500, Everett, Leadbetter

Road

WSDOT REPAVING OF SR 500 Alert has been provided by the City of Camas.

Earlier this summer, the City of Camas shared the details of the SR 500 repaving project by the Washington State Department of Transportation (WSDOT). The project will improve the area from Washougal River Bridge, just south of downtown, to the intersection of SR 500 / Everett Street and SE Leadbetter Road, just north of NE 43rd Ave.

Here are the latest details:

  • July 23 – 27: Construction of new ADA-compliant ramps and electrical work on traffic signals.
  • July 30 – August 3: Paving begins with the 3 bridges on the project.
  • August 13 – 17: Paving of the roadway.

The City of Camas is asking the public to note the following:

  • Expect delays of up to 20 minutes throughout the construction zone.
  • All work is weather dependent.

There are several ways to track the project and receive updates through WSDOT. Please review the related article on www.cityofcamas.us